Drayton Valley, AB
Water Treatment Plant |
Design Engineer - ISL Engineering and Land Services Ltd.
GE ZeeWeed 500D Ultrafiltration Plant
Design Flow: 14 MLD
To be commissioned in 2011 |
Village of Thorsby, AB
Water Treatment Plant |
Design Engineer - ISL Engineering and Land Services Ltd.
Qty. 2 ZBOX S24 Packaged Membrane Systems
Design Flow: 2.2 MLD
To be commissioned in Q1/Q2 of 2011 |
Town of Magrath, AB
Water Treatment Plant |
Design Engineer - MPE Engineering Lethbridge
GE ZeeWeed 1500 Packaged Membrane System
Design Flow: 6.1 MLD
To be commissioned in Q2 of 2011 |
Alberta Capital Region
Wastewater Treatment Plant Upgrade |
Design Engineer - Stantec Edmonton
Siemens DAF System and Polymer System
To be commissioned in Q2 2011 |
Okotoks, AB
Water Treatment Plant Upgrade |
Design Engineer - Stantec Calgary
Qty. 2 Actiflo ACP-600R-HCS Packaged Plants
Design Flow: 21,686 m3/d
Qty. 1 Additional Siemens Aluminum Rectangular Gravity Filter
Design Flow for additional filter: 1.97 MLD
Qty. 1 Additional Veolia Disk Filter for Tertiary Filtration. Total Filters: 3
Design Flow for additional filter: 24,450 m3/d
Commissioned 2010 |
Yellowknife, NWT
Water Treatment Plant |
Skid mounted pilot plant |
City of Calgary, Calgary, AB
Bonnybrook WWTP |
Primary Clarifiers (2) 120' dia.
Secondary Clarifiers (8) 65' dia.
DAFT units, rectangular
Digestors & Covers (2) 35' dia.
Fermentors & Covers (2) 35' dia. |
City of Calgary, Calgary, AB
Fishcreek WWTP |
Clarifier Covers, 2 @ 120', 2 @ 65'
Primary Screens (3)
U.V. Screen |
City of Calgary, Calgary, AB
Glenmore WTP |
Chemical Feed Equipment
Particle Counters
Chlorine Analyzers
Dechlorination System
Intake Screens |
City of Calgary, Calgary, AB
Bearspaw WTP |
Chemical Feed Equipment
New U.S. Filter/ W & T Chlorination Equipment
Particle Counters
Chlorine Analyzers
Intake Screens |
City of Edmonton, Edmonton, AB
Goldbar WWTP |
Chain & Flight Clarifiers
Grit Dewatering System
Climber Screens |
City of Edmonton, Edmonton, AB
Aqualta, E.L.Smith, Rossdale WTP |
Chemical Feed Equipment
Chlorination Equipment
Particle Counters
Chlorine Analyzers
Intake Screens |
Canmore WWTP, Canmore, AB |
Mechanical Aerators (2)
Clarifiers (2)
Biofiltration, (4) BOD, (4) Nitrification |
Grande Prairie WWTP, Grande Prairie, AB |
RBCs
ATAD’s
Bolted Tanks
Particle Counters |
City of Saskatoon, WWTP, Saskatoon, SK |
Primary Screens
Aeration Equipment
DAFT units, rectangular |
Morden WTP, Morden MB |
Complete Water Treatment Plant, Clarifiers, Filters
Controls, Chemical Feed |
Morris & Letellier WWTP, Morris, MB |
Lime System & Chemical Feed System |
Deer Lake WTP & WWTP, Deer Lake, Ont |
Packaged WTP & WWTP |
Cartier WTP, Cartier, MB |
Lime System & Chemical Feed System |
| |
| Mequipco Municipal Projects - British Columbia |
Nisga’a Village of Gitwinksihlkw |
Water Improvements Project
1 packaged Actiflo /Dusenflo Water Treatment Plant
Max Day Water Demand is 720m3/d
To be commissioned Q3 2011 |
Surrey British Columbia
Surrey Transit Centre - Coast Mountain Bus Company |
Designed by Stantec Engineering
Perma Flow Ultrafiltration Membrane Package Plant
Commissioned November 2010 |
City of Powell River
Haslam Lake Drinking Water |
Design by Dayton & Knight
Three (3) - ITT/WEDECO UV reactors – design flow 195l/s
To be commissioned Q1 2011 |
City of Salmon Arm
Metford Dam WTP |
Design by Dayton & Knight
ITT/WEDECO UV reactor – design flow 100l/s
To be commissioned 2011 |
Yukon Government
Marsh Lake WTP |
Designed by Dayton & Knight
Two (2) - GE Z-Box 12 packaged Ultrafiltration Membrane Plants
Commissioned August 2010 |
GVRD, Vancouver, BC
ANNACIS Island Plant |
Climber Screens (3) 12' wide
Centreless screw conveyors (3)
Grit dewatering equipment (3)
DAF units circular (4) @ 55' diam.
Pneumatic slide gates
Dewatering Centrifuges (4) |
GVRD, Richmond, BC
LULU Island Plant |
Primary Clarifier Components
Grit Dewatering Equipment
Dry Polymer System
Metering Pumps
Sludge Cake Handling Hoppers |
GVWD |
Ozone Generation Equipment |
GVRD, Richmond, BC
IONA Island Plant |
Plastic chain and scraper components for Primary Clarifiers |
Penticton WTP, Penticton, BC |
All Chemical Handling Systems (Lime, Alum, Caustic, Liquid Polymer, Aqua Ammonia)
Chlorination Equipment
Alum Sludge Dewatering Centrifuge |
Rossland WTP, Rossland, BC |
Ozone Generation Equipment
Chlorination |
Campbell River WWTP, BC |
Climber Screen
Secondary Clarifiers |
Prince George WWTP, BC |
Primary Clarifiers
Belt Filters |
Surrey, BC |
Archimedes Screw Pumps |
Port Alice, BC |
Submerged biological contactor
Secondary Clarifier
Sludge Storage |
Westbank WWTP |
Automatic backwash Filter
Fermenter |
| Mequipco Municipal Projects - Saskatchewan |
Water West Regional WTP (Kindersley) |
Designed by AECOM
Actiflo Clarifiers, (2 units), design flow capacity of 70 L/sec
To be commissioned early 2011 |
Swift Current WTP |
Designed by AECOM
Actiflo Clarifiers, (2 units), design flow capacity of 31.2 MLD Construction to commence late in 2010 |
Asquith WTP |
Designed by Blue Sky Management
ITT/Leopold Filter Systems – Manganese Greensand, design flow capacity of 400 usgpm
To be commissioned late 2010 |
| City of Saskatoon |
By-Pass Intake Screen
Designed by AECOM
Siemens Travelling Water Screen (2), Peak Flow sized for 120 MLD
To be commissioned late 2010 |
| Hudson Bay WTP |
Designed by Bullee Consulting
Orica Watercare “MIEX” system, design capacity of 2.7 MLD
To be commissioned in Spring of 2011 |
Battleford WTP |
Designed by Catterall & Wright
Siemens “Trident” Model TR210A packaged WTP, design capacity of 3.8 MLD
To be commissioned late 2010 |
City of Regina (Hwy 41 Project) |
Bulk Water Stations |
| LaRonge WTP |
Intake Screen System |
Yorkton WTP |
Designed by Associated Engineering
Siemens Aerators (2 x 9’ x 9’ units), ITT/Leopold Filter Systems (4 filters), and flash mixers and flocculators Commissioned this month |
| Mequipco Municipal Projects - Manitoba |
Esso Red River Intake |
Designed by JR Cousin Consultants
T-27 High Capacity Extended Passive Intake Screen handling 3,000 usgpm |
Whitemouth WTP |
Designed by Stantec Consulting (Wpg)
Packaged Actiflo Plant by JMI, model AFP-300R, design flow rate 2,160 m3/day
Successfully started up this spring |
RM of MacDonald WTP |
Designed by Genivar (Wpg)
GE Water Supplying a complete UF/LERO (low energy RO), design flowrate 60 L/sec produced water.
This replaces an existing cold lime softening plant Fast track project to be completed by March 2011 |
RM of Cartier WTP |
Design Engineer Dillon Consulting (Wpg) for Manitoba Water Services Board
GE Water Supplying a complete UF/LERO (low energy RO), design flowrate 60 L/sec produced water
This replaces an existing cold lime softening plant
Fast track project to be completed by March 2011 |
God’s Lake WTP |
Design Engineer Stantec Consulting (Wpg)
Packaged Slow Sand Filtration System, design flowrate 23. L/sec
Equipment shipped but plant not yet started up |
| RM of Elton (Forrest) |
Bulk Water Station
|
| City of Steinbach, MB |
Septic Dump Station |
| Mequipco Municipal Projects - North West Ontario |
| Dryden WWTP |
APG Neuros Blowers
Designed by Stantec Consulting
5 Blowers, Two (2) Neuros NX Turbo Blowers system packages, Model NX150-C080 and Three (3) Neuros NX Turbo Blowers system packages Model NX75-C080 complete with integrated components
Supposed to be starting up in Spring 2011 |